Engineering, Procurement and Construction - Projects

Begusarai

Commissioned 220/120/33 kV Grid Substation (GSS) along with a 100MVA Power Transformer and two 50 MVA Power Transformer within 18 months.

 

HVDS

The mega project (in Haryana) involved installation of 43,000 pole mounted distribution transformers for the conversion of existing LT (Low Tension) lines to the new 11 kV lines.

 

Leh Kargil

Providing electricity to the population in an area at 13000 ft. involving 6 substations and 215 kms of 66kV transmission line in Leh and 5 substations and 135 kms of 66kV lines in Kargil district through meticulous planning, in tough terrain and adverse weather conditions.

 

MSETCL

Commissioned 132/33 kV substation with 2 incoming lines of 132 KV, 6 lines of 33 KV, 2 transformers of 25 MVA and 1 Bus transfer 5 months ahead of schedule.

 

Cochin Project

Established 11/11 kV Switching station and 500 kVA transformer on reclaimed soil and laid 8.6 kms of underground cables throughout the city.

 


Rural Electrification Project

Transmission Line Project

Rothak Underground Cabling Project

Mirbazar Substation

 


Bisnah Project

Meerut Agra Project

Facility Management Services - Projects

 

Indian Railways-Pune Division

Work of upkeep/maintenance including Mechanized Cleaning of Chhatrapati Shivaji Maharaj Terminus station premises.

 

 

Cleaning & Maintenance of Chhatrapati Shivaji Maharaj Terminus Station

Work of upkeep/maintenance including Mechanized Cleaning of Chhatrapati Shivaji Maharaj Terminus station premises.

 

 

DMRC, Yamuna Bank

Comprehensive Cleaning and Wax Polishing of Rolling Stock (Metro Train Coaches) and Housekeeping of Depot Premises at Yamuna Bank Depot of DMRC Ltd.

 

 

Cleaning Services at Subash Chandra Bose Museum

Glass cleaning services has been provided at Subash chandra bose Museum at Red fort New Delhi for the arrival of Prime Minister Shri Narendra Modi.

 

Innovation & New Business - Projects

 

SMART BUS SHELTER

A2Z Group, commercialized first of itā€™s kind Smart Bus Shelter in Lucknow. This Smart Bus Shelter serves as a bus shelter, a zero-effluent green toilet and a kiosk for vendors/ sellers.

 

 

E-HIRAN

The innovative efforts of our Group have resulted in the designing of a unique product in the form of a bicycle, termed as E-Hiran. It is an environment-friendly product that consumes very less energy and runs on electric power. In the present era of rising fuel prices and increasing pollution, E-Hiran is the most affordable and suitable option for E-commerce industry, especially the food delivery companies.

E-Hiran is playing an important role in making the doorstep delivery very easy, cost effective and environment friendly.

 

 

E-HIRAN & Skilled Manpower ā€“ A unique combination

Our revolutionary E-Cycle, known as E-Hiran was bundled with skilled manpower. Our first service order was that from a leading app-based food delivery platform to strengthen & cost-optimize their supply chain.

 

 

MAGIC BRICK

Order received from Aligarh Municipal Corporation for Magic Bricks for boundary wall, footpaths, etc. Aligarh Municipal Corporation was awarded as the Best Medium City in Innovative Practices in the Swachh Bharat Awards for adopting this innovation at its Municipal Solid Waste Plant.

 

Municipal Solid Waste Management Services - Projects

Aligarh

A2Z Waste Management (Aligarh) Ltd. is successfully providing Integrated MSW Services in the city Aligarh from 1st May, 2010. The Project is for 30 years.

  • Door-to-door collection of MSW
  • Secondary collection &transportation of waste including street sweeping waste, drain silt
  • Collection of the user charges, on behalf of ULB
  • Processing & Disposal of Garbage
  • Manufacturing City Compost
  • Manufacturing Brick use for Boundary wall & footpath etc.

 

Muzaffarnagar

A2Z Green Waste Management Ltd is successfully providing Integrated MSW services in the city of Muzaffarnagar from 12th Feb. 2011. The Project is for 30 Years.

  • Door-to-door collection of MSW
  • Collection of the user charges, on behalf of ULB
  • Processing & Disposal of Garbage

 

 

Ludhiana

A2Z Waste Management (Ludhiana) Ltd is successfully providing Integrated MSW services in the city of Ludhiana city from 15th August. 2011. The Project is for 25 Years.

  • Door to Door Collection and Storage of MSW
  • Development of Transfer Stations and Transportation of MSW
  • Processing & Disposal of garbage
  • RDF Facility
  • Manufacturing City Compost

 

 

South Delhi Municipal Corporation

Company is successfully providing Integrated MSW services in city of West Delhi from 1st June, 2018.

  • Door to Door Collection of Waste from Streets, Households, Slums and Informal Settlements
  • Collection & Transportation of MSW from all markets, Hotels, Dhabas, Restaurants, Banquet Hall, Institution, Farm Houses in segregated manner.
  • Collection & Transportation of Street Sweeping Waste
  • Transportation of MSW from Secondary Collection Points to Waste to Energy Plant, Compost Plants & SLF at Okhla.

 

Renewable Energy generation - Projects

 

Power Plants

Installed 3 No. Biomass based power plants having capacity of 15 MW each at Nakodar located in District Jalandhar, at Fazilka located in District Fazilka and at Morinda Located in District Roopnagar. This project has been assigned to the company by The Punjab State Sugarfed Limited on the basis of competitive bidding.

 

Power Plant already commissioned

  • 15 MW RDF (Refused Derived Fuel) based Waste to Energy Plant at Nakodar in Punjab.
  • 15 MW Biomass based Power Plant at Fazilka in Punjab.

Under Erection & Commissioning

  • 15 MW Biomass based Power Project at Morinda in Punjab is still

 